Cadia Mine – NSW, Australia 2017

 Duration - 4 weeks

 Access - EWP

Following a seismic event RokTel was used by the mine to establish the condition of existing bolts and also carryout QA/QC checks of new/replacement installations. Over 300 tests were completed to aid the rehab program and meet the imposed requirements to return to production.